Bybee Sewer Project

 

Overall status:

on schedule for the general timeline of the project

Bybee area is the second of three project areas in this project

Contract end date is June 10, 2010

Expected end date for Bybee area is approximately March 22, 2010

Current Bybee status:

- Lateral Crews are on Ogden and moving east; should cross SE 39th on Friday and be moving toward 41st. Lateral crew will move to Bybee once Ogden is complete.

- Mainline Crews are east of 39th on Bybee working toward 41st

- Paving of both streets is likely the week of March 8th or 15th